Costebelle Investment Update: July 2017

This month’s Costebelle investment update brings the mechanical trades to substantial completeness! This is a huge step closer to closing up the walls with drywall and moving into the finish stage. Progress Continues on Costebelle Way Mechanical trades are 95% complete for the project. Plumbing HVAC and Electrical are all complete in the main house. Additionally, the accessory structures are also close to the last steps. Windows and doors were all delivered and installation is beginning on windows, as well as the large door frames. Moreover, we loaded the drywall into the house with a crane (video below). We are staging it for installation as soon as we obtain approval after the combo framing inspection. Our team is truly excited for the transition of this project into the finishing stage. We also ordered the elegant custom furniture package. At this point, it is all hands on deck as we race toward […]

Jul
10

Goshen Property Investment Update: July 2017

The Goshen Property Investment Update for July includes the achievement of another exciting milestone for this project. For this month’s property investment update, we bring you the progress from the past few weeks. In the past few weeks, we were able to complete the stucco, start to install exterior siding, insulate the walls and hang drywall. A new milestone! The drywall nailing was inspected and signed off by the city. The workers began installing corner beads and taping the seams. In a couple weeks’ time, the walls will be textured and interior finishes will begin to be installed. Concurrently with the interior finish, we will begin to run final utilities, install drainage, Concurrently with the interior finish, we will begin to run final utilities, install drainage, form driveways and walkways and install irrigation for landscaping. Take a look at how beautiful this property is looking now that we finished the […]

Jun
05

Goshen Investment Update: June 2017

The Goshen Investment Update for June includes the achievement of an exciting milestone for this project. In the last few weeks, we received approval from the city on the combination inspection! Conquering this milestone means we have the city’s approval to continue onto the next phase of construction on the property. This inspection and its approval means that all framing, mechanical trades, windows, and doors were properly built and in accordance with approved. Having this approval allows us to close up the building’s walls as you can see in these pictures. We are now ready to begin installing exterior and interior finishing materials. Next step is drywall installation. Take a look at how beautiful this property looks now that we closed up the building’s walls. Goshen Investment Update: June 2017 from DiversyFund Moreover, remember that we have more and new investment properties available for investing. Visit our top deals page to continue […]

Jun
05

Monterey Investment Update: June 2017

This month’s Monterey investment update is all about the details. This month we were able to reach some significant milestones for this project. We bring you the latest details on the installation of the final ridge beams, roof joints and completion of the massive roof structure. Progress Continues at Monterey. We are setting the final structural beams and have begun framing the massive roof structure. Windows and doors are now onsite and are ready for installation as soon as the roof sheathing nailed down. Finish packages are in final negotiations with various high-end contractors in the local area. Simultaneously, with the door and window installations, rough trades will continue and run all piping and wiring throughout the structure to accommodate its vast living spaces. Take a look at the pictures for this month’s investment update and take a close look at all the details that are in place for this amazing house. […]

May
08

Felspar Investment Update: May 2017

The May 2017 Felspar investment update brings progress on the sub-grade and foundation preparation, as the sub-contractors prepare the site for vertical construction. With the grading contractor finding suitable soils 5’- 6’ below grade, the crew is building the pad back up. Of course, compacting as they go. Construction Continues at Felspar Progress on Felspar continues to move forward as the foundation contractor begins work on the front unit within the next 10 days. Even more so, subcontractor pricing is coming in on target for the major trades. This leaves us moving framers onsite before the end of spring. Felspar May 2017 Investment Update from DiversyFund

May
08

Balboa Investment Update: May 2017

This month’s Balboa investment update brings the first floor all framed out including the structural steel. Also, the frames are complete with the second-floor jousting and floor sheathing. Furthermore, next week the second-floor walls will go up. Then, we will soon be on to the roof structure and details. Progress Continues at Balboa Now that the doors and windows have been purchased and ordered, the installation is scheduled for the end of May.Additionally, other major trades, which are now under contract include, roofing, plumbing and electrical. Finally, in the next couple weeks, we will be making selections on the project’s finish items. These include the cabinetry, tile, countertops and all other hard surface finishes, as well as the flooring. Balboa May 2017 Investment Update from DiversyFund

May
08

Costebelle Investment Update: May 2017

This month’s Costebelle investment update brings you a close look at a world-class construction team. The sub-contractors are all working hard keeping the project schedule on time and delivering under budget. Progress Continues in Costebelle Window and door openings have been opened up for the newly specified Fleetwood window and door package. Beams, joists, and hardware are being removed and reconfigured for a new open floor plan layout that will better showcase the property’s stunning ocean views. All plumbing was relocated in the 30” thick concrete slab. Waterproofing is complete around the entire house using the highest quality product on the market for below and above grade components. The courtyard is taking further shape with the first phase of concrete stairs starting today. Additionally, all plumbing is getting a new location in the 30” thick concrete slab. Waterproofing is complete around the entire house using the highest quality product on the market […]

Apr
13

Can I make Investment Income?

Have you recently wondered about the ways to make investment income? We know you have, and we have great news! Investment options are increasing in our market. Thanks to advanced technology and new government regulations, alternative investments are gaining ground for investors. As history shows us, we must not put all our eggs in one basket, especially when it comes to investments.  That is why options are increasing for those looking to gain investment income from different investment opportunities. “Diversifying your investment portfolio continues to prove itself as the smarter way to invest.” What is investment income? If you are wondering about investment income, you must understand what it is about. It is the income that you gain from different sources such as dividends, interest payments, capital gains, and any income made through different investment vehicles. It refers to the financial gains above the initial cost of investment. For example, […]

Mar
31

Are You Walking Away from High Return Investments?

When it comes to investing and setting up investment portfolios, it is natural to go for high return investments and low to zero risks. But, be careful as not all investments are equal. You must do your due diligence before making a decision. Both on which investments to pick and which companies to trust. Finding ads that sell the “Best Investments” is easy. Just do a quick search and you will get 100’s of results. The hard part is going through details before making a selection. This is especially true for finding an investment that best fits within your time horizon, financial goals and desired returns. What investment options produce high returns with lower risk? While there are a number of great options to choose from when it comes to investing, there are only a handful that will produce high returns with minimal risk. Of course, these are not all […]

Mar
09

Investment Project Update: Goshen Street – March 2017

This month’s investment project update on the Goshen Street property shows construction is moving right along! With all rough plumbing, electrical, HVAC and fire sprinklers complete for the two new units, Goshen is moving along in construction as we bring you this month’s investment project update. Now, that the existing unit, 1261 Goshen, is complete through drywall, including the installation of all exterior doors and windows. Additionally, the front deck for the property is now complete. Finally, the cabinets and interior finish carpentry are ordered with expected deliveries throughout this month. Getting Ready to Hang Dry Wall & More On the two units located at 1265 A & B Goshen, a roof membrane has been installed, as well as exterior doors and windows being ordered. Furthermore, the exterior doors and window will install this month. Since this gives us the ability to insulate walls, we will be able to wrap the exterior […]