Apr
12

Investment Update: Felspar April 2017

With this month’s investment update, 2112 Felspar is basically a blank canvas. Investment Update: Demolition Since the demolition work is nearly complete, we are moving into utility infrastructure and grading/site prep. Additionally, the temporary power installation is complete. Plus, the SDG&E is finally out of our construction crew’s way. from DiversyFund Preparations for Felspar Even more so, this property is ready for the construction of two beautiful new homes. With the lot consolidation and condominium map process initialized, we have submitted it to the city for final review. After approval, our team will make great progress on the Felspar property.

Mar
09

Investment Project Update: Goshen Street – March 2017

This month’s investment project update on the Goshen Street property shows construction is moving right along! With all rough plumbing, electrical, HVAC and fire sprinklers complete for the two new units, Goshen is moving along in construction as we bring you this month’s investment project update. Now, that the existing unit, 1261 Goshen, is complete through drywall, including the installation of all exterior doors and windows. Additionally, the front deck for the property is now complete. Finally, the cabinets and interior finish carpentry are ordered with expected deliveries throughout this month. Getting Ready to Hang Dry Wall & More On the two units located at 1265 A & B Goshen, a roof membrane has been installed, as well as exterior doors and windows being ordered. Furthermore, the exterior doors and window will install this month. Since this gives us the ability to insulate walls, we will be able to wrap the exterior […]

Mar
06

Investment Project Update: Monterey, CA – March 2017

This month’s investment project update on the Monterey, CA property includes a lot of fun walls! Although weather conditions continue to put a threat on our timeline, we are still bringing you the investment project update for March. We continue to have great progress on this property. Some great steps were taken between our update in February. Now, we have all walls in place, so let us show you. Take a look at the latest video and images of everything that is happening in Monterey, CA. Tilting up the walls To begin this process, still-plates are first set on the concrete floor. Once in place, the studs (vertical walls) get attached to the still-plates.  This is usually done on the ground and then the walls are tilted up into place as you can see. You are able to see the openings where the windows and doors sit. Additionally, here you […]