May
08

Felspar Investment Update: May 2017

The May 2017 Felspar investment update brings progress on the sub-grade and foundation preparation, as the sub-contractors prepare the site for vertical construction. With the grading contractor finding suitable soils 5’- 6’ below grade, the crew is building the pad back up. Of course, compacting as they go. Construction Continues at Felspar Progress on Felspar continues to move forward as the foundation contractor begins work on the front unit within the next 10 days. Even more so, subcontractor pricing is coming in on target for the major trades. This leaves us moving framers onsite before the end of spring. Felspar May 2017 Investment Update from DiversyFund

May
08

Balboa Investment Update: May 2017

This month’s Balboa investment update brings the first floor all framed out including the structural steel. Also, the frames are complete with the second-floor jousting and floor sheathing. Furthermore, next week the second-floor walls will go up. Then, we will soon be on to the roof structure and details. Progress Continues at Balboa Now that the doors and windows have been purchased and ordered, the installation is scheduled for the end of May.Additionally, other major trades, which are now under contract include, roofing, plumbing and electrical. Finally, in the next couple weeks, we will be making selections on the project’s finish items. These include the cabinetry, tile, countertops and all other hard surface finishes, as well as the flooring. Balboa May 2017 Investment Update from DiversyFund

May
08

Costebelle Investment Update: May 2017

This month’s Costebelle investment update brings you a close look at a world-class construction team. The sub-contractors are all working hard keeping the project schedule on time and delivering under budget. Progress Continues in Costebelle Window and door openings have been opened up for the newly specified Fleetwood window and door package. Beams, joists, and hardware are being removed and reconfigured for a new open floor plan layout that will better showcase the property’s stunning ocean views. All plumbing was relocated in the 30” thick concrete slab. Waterproofing is complete around the entire house using the highest quality product on the market for below and above grade components. The courtyard is taking further shape with the first phase of concrete stairs starting today. Additionally, all plumbing is getting a new location in the 30” thick concrete slab. Waterproofing is complete around the entire house using the highest quality product on the market […]

May
08

Goshen Investment Update: May 2017

This month’s Goshen investment update brings the gas lines now routed to the final connection point per SDG&E’s direction. Additionally, all rough mechanical trades are now complete for the two new units (1265 A & B), and by the 15th of May, the building inspector will grant approval to wrap the house and hang drywall. In addition, installation of the exterior doors and windows is complete. Also, scaffolding is up and ready for stucco and the existing unit (1261) has bath and shower tile complete with vanities in place, as well as fully installed carpentry that is ready for paint. As we near completion of the Goshen investment, the kitchen cabinets will be in within the next week. Shortly after this, the installation of the countertops will follow. Our target completion date is set for July 7th, 2017. Goshen: May 2017 from DiversyFund

May
08

Monterey Investment Update: May 2017

This month’s Monterey investment update brings you the latest details on the installation of the final beams and framing structures. Progress continues at Monterey We are setting the final structural beams and have begun framing the massive roof structure.Windows and Doors are on order and will be ready to install as soon as the frames come down from the rafters. We are making one last push with the HOA to modify the roofing material. The roofing material we selected will ensure a long-lasting product while saving on cost. Finish packages are finalizing as we work with the design team to assemble the perfect blend of luxury and comfort for the house. Finally, we are targeting a framing inspection date of May 26th, which will allow us to wrap the house; protecting it from the elements. We hope you enjoy these pictures showing you all the progress we accomplished in the last […]

Mar
09

Investment Project Update: Goshen Street – March 2017

This month’s investment project update on the Goshen Street property shows construction is moving right along! With all rough plumbing, electrical, HVAC and fire sprinklers complete for the two new units, Goshen is moving along in construction as we bring you this month’s investment project update. Now, that the existing unit, 1261 Goshen, is complete through drywall, including the installation of all exterior doors and windows. Additionally, the front deck for the property is now complete. Finally, the cabinets and interior finish carpentry are ordered with expected deliveries throughout this month. Getting Ready to Hang Dry Wall & More On the two units located at 1265 A & B Goshen, a roof membrane has been installed, as well as exterior doors and windows being ordered. Furthermore, the exterior doors and window will install this month. Since this gives us the ability to insulate walls, we will be able to wrap the exterior […]

Mar
09

Investment Project Update: La Jolla, CA – March 2017

This month’s La, Jolla, CA investment project update brings us closer to beginning construction With the contract almost complete and signed, this month’s investment project update brings us excitement! As this one of a kind dream home designed by renowned designer, Roman James, will be under construction in no time! Roman James Design for Costebelle This luxury home will bring Roman’s immaculate design and finishes to the San Diego market for the first time ever. As you can see with the infinity pool and relaxing back patio design, this home is sure to create a unique ambience. Then, the “hers” master bath, which showcases a modern tub and shower, along with a large and sleek vanity. Of course, from the front of the home, you will be able to see through to the backyard. Even more so, the look of the wood surrounding the door really gives it that signature look. Within the kitchen, […]

Mar
09

Investment Project Update: Coronado, CA – March 2017

The following is an Investment Project Update for all current and future investors of our Balboa Avenue, Coronado, California property. March 2017 Diversyfund knows how important it is to have the perfect location for your real estate investment. The Coronado property is no exception to this rule. Being walking distance from the beach and only a few steps away from the amazing Sea ‘N Air Golf club, this is an opportunity you can’t miss. Clearing As you can see, we cleared away the trees from our building site. We are doing the necessary rough grading, and we are staking the house location in preparation for installation of the footings, foundation, and pipes. Excavation Moreover, we started the excavation process to install all the proper equipment underground. Erosion control Finally, we are taking all the proper precautions to prevent the runoff from your cleared land from carrying mud to adjacent roads and property. […]

Mar
09

Investment Project Update: Felspar, San Diego, CA – March 2017

This month’s investment project update: Felspar is off and running! To all of our Felspar investors, the progress we are seeing at this property is amazing. Let’s go over the details for this month’s investment project update.   Getting the ground ready The pool was demolished, filled in, and dirt compacted. The field is ready. Moreover, we received authorized inspections, and now we have a suitable area to build the new extensions for this house. Demolition Moreover, we mobilized the demolition. We began on the two existing structures and we will move onto underground utilities and foundation work before the end of the first quarter this year. One house. 2 Owners Concurrently with construction, we are processing a condominium lot split to legally entitle the new dwelling units for separate ownership. What is next? Finally, we completed the topographic survey. We will submit the new Map for completeness review by the end […]

Mar
09

5 Crowdfunding Investment Advantages

Although there are many ways to invest for your future, let us go over the many advantages in crowdfunding investments. Everyone agrees that you need to have investment options in order to make sure your retirement will be solvent. Even if you have a great salary you need to not only put away part of it, but also invest it in order to make enough money to retire. Crowdfunding continues to gain strength in a world full of investment choices. It is used for different types of investments, and these have many advantages. Nonetheless, let’s go over the real estate crowdfunding investment advantages. Being that one of the safest investments is real estate, crowdfunding investments include a few advantages like no other. Typically, the value of a property increases over time. However, the cost of a property is a barrier to entering this field for many potential investors. Thus, real […]