Investment Updates

Felspar Investment Update: July 2017

This month’s Felspar investment update reports foundation work nearing completion. With unit B’s foundation 100% complete and Unit A's scheduled to pour next week. We had to use some creative thinking to stabilize the existing foundation. This is due to being required to undermine the entire existing foundation for the new larger footings. Now,...

Balboa Investment Update: July 2017

This month’s Balboa investment update brings the framing to completion. Additionally, installation of all mechanical trades has started. Also, the HVAC is already nearing completion. Currently being installed is the impressive door and window package. In addition to this, the roofer is scheduled to start next week. Progress Continues at 730...

Costebelle Investment Update: July 2017

This month’s Costebelle investment update brings the mechanical trades to substantial completeness! This is a huge step closer to closing up the walls with drywall and moving into the finish stage. Progress Continues on Costebelle Way Mechanical trades are 95% complete for the project. Plumbing HVAC and Electrical are all complete in the main...

Goshen Property Investment Update: July 2017

The Goshen Property Investment Update for July includes the achievement of another exciting milestone for this project. For this month's property investment update, we bring you the progress from the past few weeks. In the past few weeks, we were able to complete the stucco, start to install exterior siding, insulate the walls and hang...

Monterey Investment Update: July 2017

This month’s Monterey investment update reports the framing as complete. This month we have completed all of the required structural components including hardware, shear panels, beams, rafters, and joists. Thus allowing us to install the final roof sheathing and focus on the interior and exterior details and layouts. Progress Continues at 7835...

Goshen Investment Update: June 2017

The Goshen Investment Update for June includes the achievement of an exciting milestone for this project. In the last few weeks, we received approval from the city on the combination inspection! Conquering this milestone means we have the city's approval to continue onto the next phase of construction on the property. This inspection and its...

Balboa Investment Update: June 2017

This month’s Balboa investment update brings the second floor all framed out including the lower roofs. With that, the framers are currently setting the upper roof beams and getting ready to complete the structure. Additionally, delivery of the doors and window will be before the end of June. The mechanical trades are prepared to start on the...

Monterey Investment Update: June 2017

This month's Monterey investment update is all about the details. This month we were able to reach some significant milestones for this project. We bring you the latest details on the installation of the final ridge beams, roof joints and completion of the massive roof structure. Progress Continues at Monterey. We are setting the final...

Costebelle Investment Update: June 2017

The Costebelle investment update for June brings you a close look at a world-class construction team as Roman James' team works hard to create a beautiful home. Progress Continues in Costebelle Mechanical trades are close to 90% complete for the project. Installation of plumbing components is complete with rough-in shower and tub valves affixed...

Felspar Investment Update: June 2017

This month’s investment update for Felspar brings progress on the sub-grade and foundation preparation to completion. In addition to this, the grading and major utility work is complete, as well as the building pads certified to accept the new structures. Construction Continues at Felspar Progress on Felspar continues to move forward as the...