Goshen Investment Update: October 2017

Countertops are complete, bathroom accessories and interior handrails are installed and all hardwood floor areas are done.

The existing retaining wall was waterproofed. The landscape drainage and new retaining wall between existing house and Unit 1 are now finished. Concrete forms on the garages and common areas are ready to be poured.

We purchased furniture for this house and expect delivery later this month. Certificates of occupancy should be issued shortly thereafter. Our sales strategy is to furnish and rent the property. Thereafter,  we will sell it as a cash-flowing investment property, the highest and best use of the property. This strategy is in place to command the maximum sales price.