Goshen Investment Update: May 2017

This month’s Goshen investment update brings the gas lines now routed to the final connection point per SDG&E’s direction. Additionally, all rough mechanical trades are now complete for the two new units (1265 A & B), and by the 15th of May, the building inspector will grant approval to wrap the house and hang drywall.

In addition, installation of the exterior doors and windows is complete. Also, scaffolding is up and ready for stucco and the existing unit (1261) has bath and shower tile complete with vanities in place, as well as fully installed carpentry that is ready for paint.

As we near completion of the Goshen investment, the kitchen cabinets will be in within the next week. Shortly after this, the installation of the countertops will follow. Our target completion date is set for July 7th, 2017.