Goshen Investment Update – December 2017

This month we’ve been putting the finishing touches on the Goshen property.

This month we’ve been putting the finishing touches on the existing house, including garage door installation, framing the master bedroom balcony railing, and grass installation. Utilities were processed this month with SDG&E and the City of San Diego public utilities.

We’re now waiting for SDG&E to connect meters and backfill and for the subcontractor to connect water from the property to the street. This includes a re-do of the sidewalks, street and driveway. We are almost there!