Felspar Investment Update: October 2017

This month’s investment update for our project at 2112 Felspar Street reports that frames are almost done in Unit B.

With the first and second floor finished and trusses installed, it is about 90% of the way done. Then in Unit A, the first floor is completely framed and 95% of the second floor is complete. Additionally, sheathing roof deck floor is being done to create a slope.

Now, our team is scheduling all rough plumbing, electric and HVAC to begin soon. We have also selected all finishes to truly give this property a charming look. This way we are working together with subcontractors to make final decisions to ensure we stay on schedule.