Felspar Investment Update November 2017

This project is starting to take shape!

Unit A has rough-in plumbing at 70% and HVAC at 20%. Unit B rough-in plumbing and HVAC are done and we’ve begun electrical layout and locating electric and gas meters. Windows and exterior doors will be delivered and installed soon. Stucco is scheduled for later this month and roofing will begin by early December.