Felspar Investment Update: June 2017

This month’s investment update for Felspar brings progress on the sub-grade and foundation preparation to completion. In addition to this, the grading and major utility work is complete, as well as the building pads certified to accept the new structures.

Construction Continues at Felspar

Progress on Felspar continues to move forward as the foundation contractor has begun work on the front unit. Surveyors will soon be out to establish building corners for the back unit. This will allow the foundation work to forward simultaneously on both units. There is also a masonry crew beginning to dig foundation for the retaining wall that splits the two building pads. Subcontractor pricing is coming in on target for the major trades and we will begin to make interior finish selections in the weeks to come.

Felspar Investment Update: June 2017 from DiversyFund

Related Articles

DiversyFund Q2 Investment Update (2019)
  • Investment Updates

DiversyFund Q2 Investment Update (2019)

DiversyFund Q2 Investment Update Cash Flowing Multifamily. The Growth REIT continues to focus on acquiring multifamily value add projects that already have in place cash flows and can target 10% plus cash on cash yields while holding and 16-20% IRR’s over a 3 to 5 year hold. New Multifamily Deals The Growth REIT is under…

DiversyFund Q1 Investment Update (2019)
  • Investment Updates

DiversyFund Q1 Investment Update (2019)

DiversyFund Q1 Investment Update The Growth Fund is invested in a brand new value-add asset named Summerlyn in Texas. Closing is anticipated next month for this new 200 unit project that is targeting an 18% IRR to the Growth Fund. Our real estate team is out in Texas currently looking at 2 other value-add opportunities…

DiversyFund Q4 Investment Update (2018)
  • Investment Updates

DiversyFund Q4 Investment Update (2018)

Park Blvd Investment Update Q4 2018 The Park Blvd project is close to receiving full permits. While the holidays slowed down response time from the City, our team is clarifying what will most likely be the last round of comments before locking in the wood frame permit. As mentioned in previous updates, the foundation permit…