Felspar Investment Update | December 2017

For the month of December, our Felspar project brings many new updates, which are bringing it closer to the finish line.

First of all, we just passed our framing and rough-in inspections! Moreover, the fire sprinklers are complete and ready for inspection.

Since December typically brings a lot of rain, we papered all of the roof areas to protect them. The exterior stucco of the property will be starting soon.

Finally, before we took off for the holiday, we did a preliminary walk through with the flooring company to make sure everything is ready for them when it’s time for their work to begin.