Balboa Investment Update: May 2017

This month’s Balboa investment update brings the first floor all framed out including the structural steel. Also, the frames are complete with the second-floor jousting and floor sheathing. Furthermore, next week the second-floor walls will go up. Then, we will soon be on to the roof structure and details.

Progress Continues at Balboa

Now that the doors and windows have been purchased and ordered, the installation is scheduled for the end of May.Additionally, other major trades, which are now under contract include, roofing, plumbing and electrical. Finally, in the next couple weeks, we will be making selections on the project’s finish items. These include the cabinetry, tile, countertops and all other hard surface finishes, as well as the flooring.