Balboa Investment Update: July 2017

This month’s Balboa investment update brings the framing to completion.

Additionally, installation of all mechanical trades has started. Also, the HVAC is already nearing completion. Currently being installed is the impressive door and window package. In addition to this, the roofer is scheduled to start next week.

Progress Continues at 730 Balboa Avenue

The selection of the interior finishes is complete. These include:

  • a Thermador appliance package,
  • a high-end plumbing package, and
  • a craftsman style wood trim package.

Also, selections and accommodations for the exterior finishes are complete. With this, there will be five different materials coming together, which will enhance the beauty of this 4,000+ square foot, modern beach cottage on Coronado Island.

We hope you enjoyed this month’s update for the beautiful property in Balboa. Remember that we have an exclusive offer this month to increase your earnings. Click here get 1% yield bump on all new investments this month.